Centerbridge Seaport Acquisition Fund/BrightSpring Health Services, Inc.
- Forum
- FTC administrative order
- Docket
- C-4829
- Order date
- 2026-06-10 (printed in the order)
- Status in the FTC case catalog
- Entered or issued, listed on the case page under 2026-06-10
- Length of the order
- Until 2036-06-10 (10 years from issuance of the order)
- Source
- Order text (PDF, ftc.gov) | FTC case page
- Source file sha256
ab9c50ca2cb8d93c82a5f76480143536aaa04da1d83d47b89d7e0ba784ea27df
Parties bound, as written in the order
- Centerbridge Seaport Acquisition Fund, L.P. (Respondent, DE), 375 Park Avenue, 11th Floor, New York, New York 10152
- National Mentor Holdings, Inc. (Respondent, DE), 6600 France Avenue South, Edina, Minnesota 55435
- BrightSpring Health Services, Inc. (Respondent, DE), 805 N Whittington Pkwy Louisville, Kentucky 40222
Duties (39)
II.A: Divestiture
Divest the Divestiture Facility Assets as an ongoing business, absolutely and in good faith, to Dungarvin within 10 days after the Acquisition Date.
- Who
- Respondent Sevita
- When
- Due 10 days, counted from the event “Acquisition Date”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 10 days after the Acquisition Date, Respondent Sevita shall divest the Divestiture Facility Assets as an ongoing business, absolutely and in good faith, to Dungarvin.
Quoted from the order text (PDF), clause II.A.
II.B(1)-rescind: Divestiture
If the Commission notifies at finalization that the Acquirer is not acceptable, rescind the divestiture within 5 days of notification.
- Who
- Respondent Sevita
- When
- Due 5 days, counted from the event “Commission notification that the Acquirer is not acceptable”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
then Respondent Sevita shall rescind the divestiture to that Acquirer within 5 days of notification
Quoted from the order text (PDF), clause II.B(1)-rescind.
II.B(1)-divest: Divestiture
In that event, the Divestiture Trustee is to divest the relevant assets no later than 180 days from issuance, at no minimum price, to a Commission-approved Person.
- Who
- Divestiture Trustee appointed by the Commission
- When
- Due 2026-12-07 (180 days after issuance of the order)
- Status
- Not yet due. The due date worked out from the order and its start date has not arrived yet.
the Divestiture Trustee appointed by the Commission shall divest the relevant Divestiture Facility Assets no later than 180 days from the date this Order is issued, absolutely and in good faith, at no minimum price
Quoted from the order text (PDF), clause II.B(1)-divest.
II.C: Prohibition
Do not consummate the Acquisition until approvals are obtained for assignment to the Acquirer of each Divestiture Facility real property lease.
- Who
- Respondent Sevita
- When
- Due by the event “consummation of the Acquisition (obtain before)”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Respondent Sevita shall not consummate the Acquisition until it has obtained, for all the Divestiture Facilities, all approvals for the assignment to the Acquirer
Quoted from the order text (PDF), clause II.C.
II.D: Required action
Release, and do not exercise, rights or causes of action against relevant landlords under leases of transferred facilities, for matters accruing on or after transfer.
- Who
- Respondent Sevita
- When
- No one-time deadline
- Status
- No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
Respondent Sevita shall release, and shall not exercise, any right or cause of action against any relevant landlord that is provided to Respondent Sevita by a lease agreement
Quoted from the order text (PDF), clause II.D.
II.E: Cooperation
Assist the Acquirer's due diligence by giving timely access to information, personnel, assets, Contracts and Business Information.
- Who
- Respondent Sevita
- When
- No one-time deadline
- Status
- No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
Respondent Sevita shall assist the Acquirer to conduct a due diligence investigation of the Divestiture Facility Assets the Acquirer seeks to purchase
Quoted from the order text (PDF), clause II.E.
II.F: Required action
At the Acquirer's option and on each Divestiture Date, assign included contracts or help obtain third-party approval or a new contract.
- Who
- Respondent Sevita
- When
- Due by the event “Divestiture Date of each Divestiture Facility”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
With respect to all contracts included in the Divestiture Facility Assets, at the Acquirer’s option and on the Divestiture Date of each Divestiture Facility, Respondent Sevita shall:
Quoted from the order text (PDF), clause II.F.
II.G: Cooperation
Assist the Acquirer in obtaining all licenses, permits, authorizations or certifications needed to operate the Divestiture Facility Assets.
- Who
- Respondent Sevita
- When
- No one-time deadline
- Status
- No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
Respondent Sevita shall assist the Acquirer in obtaining all licenses, permits, authorizations, or certifications related to or necessary for the operation of the Divestiture Facility Assets.
Quoted from the order text (PDF), clause II.G.
III.B: Prohibition
Do not modify or amend the Divestiture Agreement after issuance without prior Commission approval, except as the Commission Rules allow.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Respondent Sevita shall not modify or amend the terms of the Divestiture Agreement after the Commission issues this Order without the prior approval of the Commission
Quoted from the order text (PDF), clause III.B.
IV.A: Required action
Until all assets are divested and Business Information transferred, keep Business Information maintained and updated and give the Acquirer access to it and to employees who hold it.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs until the event “transfer of all Business Information and divestiture of all Divestiture Facility Assets”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Until Respondent Sevita has transferred all Business Information and divested all Divestiture Facility Assets to the Acquirer, Respondent Sevita shall ensure that the Business Information is maintained and updated
Quoted from the order text (PDF), clause IV.A.
IV.B-C: Required action
At the Acquirer's option, provide Transitional Assistance at the price in the Divestiture Agreement (or Direct Cost) for a period sufficient to meet the Order's requirements.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs until the event “period sufficient to meet the requirements of Section IV”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
At the option of the Acquirer, Respondent Sevita shall provide the Acquirer with Transitional Assistance sufficient to (1) transfer efficiently the Divestiture Facility Assets to the Acquirer
Quoted from the order text (PDF), clause IV.B-C.
IV.D: Required action
Allow the Acquirer to terminate Transitional Assistance in whole or part on commercially reasonable notice and without cost or penalty.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs until the event “end of Transitional Assistance”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Respondent Sevita shall allow the Acquirer to terminate, in whole or part, any Transitional Assistance of the Divestiture Agreement upon commercially reasonable notice
Quoted from the order text (PDF), clause IV.D.
IV.E: Prohibition
Do not stop providing Transitional Assistance because of an Acquirer breach, and do not limit damages the Acquirer could receive for Respondent Sevita's breach.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs until the event “end of Transitional Assistance”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Respondent Sevita shall not cease providing Transitional Assistance due to a breach by the Acquirer of the Divestiture Agreement
Quoted from the order text (PDF), clause IV.E.
V.A: Cooperation
Until one year after the Divestiture Date, cooperate with and assist the Acquirer to evaluate and offer employment to any Divestiture Facility Employee.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs 1 year, counted from the event “Divestiture Date”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Until one year after the Divestiture Date, Respondent Sevita shall cooperate with and assist the Acquirer to evaluate independently and offer employment to any Divestiture Facility Employee.
Quoted from the order text (PDF), clause V.A.
V.B(1): Required action
Within 10 days of an Acquirer request, provide a list of requested Divestiture Facility Employees and Employee Information, until 90 days after the Divestiture Date.
- Who
- Respondent Sevita
- When
- Due 10 days, counted from the event “request from the Acquirer”; date not public
- How long
- Runs 90 days, counted from the event “Divestiture Date”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 10 days after a request from the Acquirer, provide a list of the requested Divestiture Facility Employees and provide Employee Information for each;
Quoted from the order text (PDF), clause V.B(1).
V.B(2): Required action
Within 10 days of an Acquirer request, provide an opportunity to privately interview Divestiture Facility Employees and make offers of employment.
- Who
- Respondent Sevita
- When
- Due 10 days, counted from the event “request from the Acquirer”; date not public
- How long
- Runs 90 days, counted from the event “Divestiture Date”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
No later than 10 days after a request from the Acquirer, provide an opportunity to privately interview any of the Divestiture Facility Employees outside the presence or hearing of any employee or agent of Respondent Sevita
Quoted from the order text (PDF), clause V.B(2).
V.B(3)-(6): Required action
Until 90 days after the Divestiture Date, remove impediments to employees joining the Acquirer, keep benefits and incentives in place, and not interfere with hiring.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs 90 days, counted from the event “Divestiture Date”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Remove any impediments within the control of Respondent Sevita that may deter Divestiture Facility Employees from accepting employment with the Acquirer, including removal of any non-compete or confidentiality provisions
Quoted from the order text (PDF), clause V.B(3)-(6).
V.C(1): Prohibition
For 90 days after the Divestiture Date, do not solicit or induce Facility-level employees of the Acquirer to leave, subject to stated exceptions.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs 90 days, counted from the event “Divestiture Date”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
For a period of 90 days after Divestiture Date, directly or indirectly, solicit or otherwise attempt to induce any Person employed at the Facility level by the Acquirer to terminate his or her employment with the Acquirer
Quoted from the order text (PDF), clause V.C(1).
V.C(2): Prohibition
For 180 days after the Divestiture Date, do not solicit or induce employees above Facility level of the Acquirer to leave, subject to stated exceptions.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs 180 days, counted from the event “Divestiture Date”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
For a period of 180 days after the Divestiture Date, directly or indirectly, solicit or otherwise attempt to induce any Person employed above the Facility level by the Acquirer to terminate his or her employment with the Acquirer.
Quoted from the order text (PDF), clause V.C(2).
VI: Required action
Until the assets are fully transferred, operate the Divestiture Facility Assets in the ordinary course and maintain their viability, staffing, relationships and condition.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs until the event “Respondent Sevita fully transfers each of the Divestiture Facility Assets to the Acquirer”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Operate the Divestiture Facility Assets in the ordinary course of business consistent with past practices, and take all actions necessary to maintain the full economic viability, marketability, and competitiveness of the Divestiture Facility Assets;
Quoted from the order text (PDF), clause VI.
VII.A: Prohibition
Do not disclose or use Confidential Information relating to any Divestiture Facility, except as permitted by the Orders, legal proceedings or law.
- Who
- Respondents
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Respondents shall not (x) disclose (including to Respondents’ employees) or (y) use for any reason or purpose, any Confidential Information received or maintained by Respondents relating to any Divestiture Facility
Quoted from the order text (PDF), clause VII.A.
VII.B: Required action
Limit permitted disclosure of Confidential Information to the extent required, to those who need it, and only after they sign a confidentiality agreement.
- Who
- Respondents
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Respondents shall limit such disclosure or use (1) only to the extent such information is required; (2) only to those employees or Persons who require such information
Quoted from the order text (PDF), clause VII.B.
VII.C: Required action
Enforce the confidentiality terms and take steps such as access and data controls and training to ensure employees and others comply.
- Who
- Respondents
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Respondents shall enforce the terms of this Section VII and take necessary actions to ensure that its employees and other Persons comply with the terms of this Section VII
Quoted from the order text (PDF), clause VII.C.
VIII.D(1): Cooperation
Cooperate with and assist the Monitor, including full access to personnel, information and facilities.
- Who
- Respondents
- When
- No one-time deadline
- How long
- Runs until the event “Commission staff determines Respondents have satisfied all obligations under Sections II, IV, and VI, and files a final report”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Cooperate with and assist the Monitor in performing his or her duties for the purpose of reviewing Respondents’ compliance with their obligations under the Orders
Quoted from the order text (PDF), clause VIII.D(1).
VIII.D(3): Payment
Pay the Monitor's fees and expenses under a Commission-approved agreement or, if none, the Monitor's customary fees and expenses.
- Who
- Respondents
- When
- No one-time deadline
- How long
- Runs until the event “Commission staff determines Respondents have satisfied all obligations under Sections II, IV, and VI, and files a final report”; date not public
- Money
- Judgment: not stated. Payable: not stated.
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Pay the Monitor’s fees and expenses as set forth in an agreement approved by the Commission, or if such agreement has not been approved, pay the Monitor’s customary fees
Quoted from the order text (PDF), clause VIII.D(3).
IX.C: Required action
Within 10 days after a Divestiture Trustee is appointed, execute a trust agreement transferring necessary rights and powers to the Trustee.
- Who
- Respondent Sevita
- When
- Due 10 days, counted from the event “appointment of a Divestiture Trustee”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Not later than 10 days after the appointment of a Divestiture Trustee, Respondent Sevita shall execute a trust agreement that, subject to the prior approval of the Commission, transfers
Quoted from the order text (PDF), clause IX.C.
IX.D(3): Cooperation
Cooperate with any Divestiture Trustee and do not interfere with or impede the divestitures.
- Who
- Respondent Sevita
- When
- No one-time deadline
- Status
- No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
Respondent Sevita shall develop such financial or other information as the Divestiture Trustee may request and shall cooperate with the Divestiture Trustee.
Quoted from the order text (PDF), clause IX.D(3).
X.A: Notice
For 10 years from issuance, give the Commission advance written notice before acquiring any interest in an ICF/IDD in the same CBSA as a Divestiture Facility.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
For a period of 10 years from the date this Order is issued, Respondent Sevita shall not, without providing advance written notification to the Commission
Quoted from the order text (PDF), clause X.A.
X.C: Notice
Provide the notification at least 30 days before consummating the transaction, and wait 30 days after supplying any additional information requested.
- Who
- Respondent Sevita (reports to: Commission)
- When
- Due 30 days, counted from the event “consummation of the transaction (before)”; date not public
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Respondent Sevita shall provide the Notification required under Paragraph X.A to the Commission at least 30 days prior to consummating the transaction
Quoted from the order text (PDF), clause X.C.
XI: Prohibition
For 10 years from issuance, do not acquire any leasehold, ownership or other interest in any Divestiture Facility.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
for a period of 10 years from the date this Order is issued, Respondent Sevita shall not acquire, directly or indirectly, through subsidiaries or otherwise, any leasehold, ownership interest, or any other interest
Quoted from the order text (PDF), clause XI.
XII.A(1): Notice
Notify Commission staff by email of the Acquisition Date and the Divestiture Date within 5 days after each occurs.
- Who
- Respondent Sevita (reports to: Commission)
- When
- Due 5 days, counted from the event “Acquisition Date; Divestiture Date”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Notify Commission staff via email at bccompliance@ftc.gov of the Acquisition Date and the Divestiture Date no later than 5 days after the occurrence of each
Quoted from the order text (PDF), clause XII.A(1).
XII.A(2): Reporting
Submit the Divestiture Agreement to the Commission no later than 30 days after the Divestiture Date.
- Who
- Respondent Sevita (reports to: Commission)
- When
- Due 30 days, counted from the event “Divestiture Date”; date not public
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Submit the Divestiture Agreement to the Commission at ElectronicFilings@ftc.gov and bccompliance@ftc.gov no later than 30 days after the Divestiture Date.
Quoted from the order text (PDF), clause XII.A(2).
XII.B(1)a: Reporting
File verified Interim Compliance Reports 30 days after issuance and every 60 days after until Section II is fully complied with.
- Who
- Respondent Sevita (reports to: Commission)
- When
- Due 2026-07-10 (30 days after issuance of the order)
- How long
- Runs until the event “Respondent Sevita has complied fully with Section II”; date not public
- Repeats
- Every 60 days
- Status
- No public record of completion found. We have not found a public record showing this duty being carried out. Most compliance is reported privately to the agency and never published, so the absence of a public record does not mean the duty was not met.
Interim Compliance Reports 30 days after this Order is issued, and every 60 days thereafter until Respondent Sevita has complied fully with Section II
Quoted from the order text (PDF), clause XII.B(1)a.
XII.B(1)b: Reporting
File verified Annual Compliance Reports one year after issuance and annually for the next 9 years.
- Who
- Respondent Sevita (reports to: Commission)
- When
- Due 2027-06-10 (1 year after issuance of the order)
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Repeats
- Every 1 year
- Status
- Not yet due. The due date worked out from the order and its start date has not arrived yet.
Annual Compliance Reports one year after the date this Order is issued, and annually thereafter for the next 9 years on the anniversary of that date
Quoted from the order text (PDF), clause XII.B(1)b.
XII.B(1)c: Reporting
File additional Compliance Reports as the Commission or its staff request.
- Who
- Respondent Sevita (reports to: Commission)
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
Additional Compliance Reports as the Commission or its staff may request.
Quoted from the order text (PDF), clause XII.B(1)c.
XII.B(3): Recordkeeping
For 5 years after filing each Compliance Report, retain material written communications and internal memoranda about compliance and give copies to staff on request.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Runs 5 years, counted from the event “filing of each Compliance Report”; date not public
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
For a period of 5 years after filing a Compliance Report, Respondent Sevita shall retain all material written communications with each party identified in each Compliance Report
Quoted from the order text (PDF), clause XII.B(3).
XIII: Notice
Notify the Commission at least 30 days before dissolution or acquisition, merger or consolidation of National Mentor Holdings, Inc., or other changes that may affect compliance.
- Who
- Respondent Sevita (reports to: Commission)
- When
- Due 30 days, counted from the event “proposed dissolution, acquisition, merger, consolidation or other change (before)”; date not public
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- Due date not public. The order sets a deadline counted from a date or event that is not public, such as an effective date, a date of service or a divestiture, so the due date cannot be worked out and is not shown as passed.
Respondent Sevita shall notify the Commission at least 30 days prior to:
Quoted from the order text (PDF), clause XIII.
XIV: Cooperation
On written request and 5 days' notice, permit Commission representatives to inspect and copy records and facilities and interview officers, directors or employees.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
upon written request and 5 days notice to Respondent Sevita, made to its principal place of business as identified in this Order, registered office of its United States subsidiary, or its headquarters office, Respondent Sevita shall, without restraint or interference, permit any duly authorized representative of the Commission
Quoted from the order text (PDF), clause XIV.
XVI: Term of the order
The Order terminates 10 years from the date it is issued.
- Who
- Respondent Sevita
- When
- No one-time deadline
- How long
- Until 2036-06-10 (10 years from issuance of the order)
- Status
- In force. The order requires this for as long as its stated period runs. This says nothing about whether it is being followed.
IT IS FURTHER ORDERED that this Order shall terminate 10 years from the date it is issued.